Uncategorized

Russian Warehouse Project — Simple Construction Plan22m × 46m = 1,012 m² | Clear Height 7.5m | June 30, 2026

I. Basic Project Parameters

ParameterValueDescription
Building Dimensions22m × 46mSingle-span portal frame
Building Area / Clear Height1,012 m² / 7.5mFrom column base to roof truss lower chord
Structural Form / Roof SlopeSingle-span portal frame (PEB) / 5%~10%Double-slope roof
Column Spacing / Number of Frames6.0m / 7~8 framesIndependent column foundations
Enclosure SystemMetal profiled steel sheet roof + wallsOptional insulated sandwich panels

II. Bill of Quantities and Cost Estimate

Component TypeEstimated Quantity (tons)Steel IndexRemarks
Main Frame (Steel Columns + Steel Beams)28.328 kg/m²–
Purlins and Wall Beams (Cold-formed Thin-walled)10.110 kg/m²–
Bracing System (Tie Rods + Angle Steel)7.17 kg/m²–
Total Structural Steel45.545 kg/m²Main material: Q355D
Roof Panels + Wall Panels (Enclosure)~8.0–Rough estimate

Steel Quantity Note: This estimate is based on a conventional single-span 22m × 46m warehouse with 7.5m clear height. If snow load is higher, steel quantity may increase by 10%–20%. Final quantities shall be based on detailed design drawings.

III. Material Scheme and Quotation

Quotation Scope: Structural steel materials (Q355D), fabrication, sea + land transportation (optional), enclosure system (roof panels + wall panels), Chinese construction team (5 persons × 1 month), local equipment rental, auxiliary materials (bolts, welding consumables).

China Standard vs. Russia Standard Material Comparison

Chinese Standard (GB)Russian Standard (GOST 27772)Yield StrengthLow-temperature ImpactApplicable Scenarios
Q235BC235≥235 MPa20°CGeneral components
Q235DC235-4≥235 MPa-20°CSecondary components in low-temp areas
Q235E–≥235 MPa-40°CSecondary components in extreme cold
Q355BC355≥355 MPa20°CGeneral main structure
Q355D [Recommended]C355-4≥355 MPa-20°CMain structure for Russia
Q355EC355-5≥355 MPa-40°CMain structure in extreme cold areas

Recommendation: Main structure to use Q355D (Russian standard C355-4) to ensure low-temperature toughness at -20°C.

IV. Construction Team Quotation

Expense ItemCalculation MethodAmount (RMB 10,000)
Labor Wages5 persons × RMB 1200/day × 26 days (1 month)15.6
Visa + Air Tickets5 persons × RMB 20,00010
Accommodation in Russia5 persons × RMB 5,000/month × 1 month2.5
Overseas Insurance5 persons × RMB 8,0004
Subtotal–32.1

The above quotation covers a core Chinese team of 5 persons. It is recommended to hire an additional 3–5 local Russian auxiliary workers to reduce overall project cost.

Exchange Rate Reference: 1 CNY ≈ 11.2 RUB (June 2026 reference)

V. Project Images

Portal frame (before installation of roof and wall panels)

Column base anchor bolts and connection between steel column and foundation
Composite rock wool sandwich panel (for roof or wall)

Notes
This document is a simplified preliminary estimate prepared based on the project parameters 22m × 46m × 7.5m and standard warehouse design experience. Final quotation shall be based on formal design drawings, local regulations, and actual geotechnical conditions. All prices are reference prices as of June 2026.